WBS and PERT diagram I have a WBS (Work Breakdown structure) which has milestones, outlined tasks (speaking in MS Project terms) and work packages. I want to design a PERT (Program Evaluation Review Technique) chart based on that WBS. Should I add milestones and outline tasks to PERT chart?

Early versions of PERT diagrams had "PERT Events" that were **_all_** milestones or gates with task information embedded in the arrows. This has changed over the years but most PERT charts I have seen "in the wild" continue to show milestones.

Outline tasks or phases are rarely shown on PERT charts or other network diagrams, in my experience since they generally interfere with reading the diagram without providing useful information.

I could not find much academic/formal guides for this kind of diagramming. Lots of information on building PERT estimates but my Google-fu is coming up short on the diagramming. Considering how old PERT diagrams and methods are, I find that surprising.

xcX3v84RxoQ-4GxG32940ukFUIEgYdPy e0d60dfccac9774d1fac7e327eee5c68