Various resource assignments for different portions of a task Consider two tasks (Task 1 and Task 2), as well as two resources (Developer 1 and Developer 2). Task 1 and 2 respectively require 1 and 2 days from start to finish. I want to make the following resource assignment in Microsoft Project: * Developer 1 allocates 50% of his time working on Task 1. * In parallel, and using any remaining time, Developer 1 helps Developer 2 to work on Task 2. In this way, once Developer 1 finished working on Task 1, he should allocate 100% of his time to work on Task 2. That is, Task 2 requires (1.5 + 2) * 8 = 28 man-hours. Here's a screenshot of what I achieved in MS Project: ![]( > **My question is:** How to allocate 50% of Developer 1 for the first day of Task 2, and 100% of him for the second day of Task 2.

You can adjust the hours of work for each resource by day in the Task Usage view:

![enter image description here](

Gantt Chart then looks like this:

![enter image description here](

xcX3v84RxoQ-4GxG32940ukFUIEgYdPy 8d4d1b4ae9e1a4d7e351fb053eb538b9