What does (Normal time-Crash time=0) implies? In Crashing a project, if for an activity [Normal time - Crash time = 0], what does it mean? Since Crash cost per day = |(Crash cost-Normal cost)/(Normal Time- Crash time)| The Crash cost per day becomes infinite. what does this implies?

You would be using this as a prediction, right? If you are predicting your normal time and your crash time are the same, as evidenced by the zero, then you are essentially predicting increased costs with no gain in days, which produces an error in the ratio. That implies: DON'T DO IT!

Under what scenario would you try to get approved money to crash a schedule that you are predicting you cannot crash?